A new bill amending Türkiye's renewable energy law was submitted to parliament in mid-November 2026. The Industry, Trade, Energy, Natural Resources, Information and Technology Committee approved it on the night of 18–19 November, and the General Assembly began debating it this week. For owners of solar plants, and for installers and EPCs who serve them, the bill could change the economics of existing plants and the rules for new capacity.

YEKA competitions move into law

Following a Constitutional Court ruling, the bill sets out in law that renewable energy resource areas and grid connection capacity will be allocated through competitions. The scope and the technical and administrative conditions of each competition will be set in its specification. The court's deadline of 10 December 2026 is one reason the bill is moving quickly.

Older unlicensed plants can move to licensed status

Under the bill, unlicensed plants of 750 kW and above that have operated for ten years can switch to licensed generation. In return they pay a licence fee and, for the rest of the licence period, the difference whenever the hourly market clearing price is higher than the applicable YEKDEM price. Earlier drafts capped the licence fee at 30%; check the final text once it is published in the Official Gazette.

Capacity increases

The bill also addresses fees for capacity increases at existing plants, with the first draft capping them at 50%. For many owners, this is the most practical opportunity: adding panels, replacing older inverters or adding storage at a site that already has a grid connection.

What plant owners should review now

  • Plant age and size: which plants pass ten years of operation and the 750 kW threshold.
  • Equipment condition: inverters and modules installed a decade ago are often the first candidates for replacement, and higher-efficiency TOPCon modules can raise output on the same roof or land.
  • Storage: batteries let plants shift output to higher-price hours, which matters if revenues become more market-linked.
  • Timing and currency: equipment is priced in US dollars and the lira is above 50 per dollar, so plan purchases and financing together.

How Nastech can help

Nastech supplies modules, inverters and Jebel-branded LFP batteries to installers and EPCs in Türkiye through its official distributor Turas Tech. Contact us to size an expansion, repowering or storage project once the final rules are clear.

Featured product

LONGi Hi-MO X10 660W Arka Kontaklı Bifacial Panel

LONGi Hi-MO X10 660W back-contact bifacial panel: a high-efficiency back-contact (HPBC) module for repowering and capacity increases. View product

This article summarises the bill as approved in committee and reported in the press in November 2026. The text may change during debate in the General Assembly. It is not legal advice.

Lithium Batteries Compatible with Deye Inverters: Based on Dyness's Official Lists
LV and HV combinations according to the battery manufacturer's official compatibility lists